Creek Crossing Reroute and Repair
As part of the City of Tyler Consent Decree project, sanitary sewer mains that cross creeks and drainage channels were inspected and their condition assessed for likelihood of pipe failure resulting in unauthorized discharge, or stormwater inflow. Creek crossing assessments rated poor were collected into projects where the crossing could be repaired rerouted based upon field conditions. The project includes the repairs and reroutes of approximately 2,556 linear feet of gravity sewer main ranging in size from 6-inches to 12-inches in diameter, with new pipe, manholes, and appurtenances. Role: Project Manager/Cost: $1,055,409