Bastrop, Texas Wastewater Treatment Plant

Wastewater Treatment Plant Bastrop

The projected growth of the City of Bastrop resulted in wastewater flow rates that exceeded the capacity of the city's then-current wastewater collection system and treatment facilities. To meet this demand, the City of Bastrop hired KSA to construct a new wastewater treatment plant (number 3) to replace the city's two existing plants (plant numbers 1 and 2). A new lift station and force main were to divert wastewater from plant 1 and 2 to plant 3. New interceptor sewers were also planned to be constructed to meet the future wastewater service needs of the city.

The construction work was divided into four construction projects:
• Contract A: The new wastewater treatment plant number 3 consisting of all work on the new plant site and the plant outfall line.
• Contract B: A new transfer lift station and force main associated with transporting wastewater from the existing plants to the new plant number 3.
• Contract C: Westside collector and interceptor sewers west of the Colorado River.
• Contract D: Decommissioning of plants number 1 and 2.

Project Owner
Bastrop, Texas
Treatment Capacity
2 MGD ADF